Buc-ee’s Inches Closer to Proposed El Paso County Travel Center
Plans for a potential Buc-ee’s travel center near Interstate 25 and County Line Road have advanced, with the company submitting a site development plan to El Paso County for review.
The county received the plan on Oct. 12 and will now evaluate whether the proposed project meets technical requirements for development, including lighting, landscaping, parking, traffic and necessary roadway improvements.
The review marks another step toward the proposed project, which has drawn significant attention and opposition from residents in the Tri-Lakes area.
County officials will review the submitted plans administratively to determine whether they comply with applicable design standards. If the proposal meets those requirements, it can receive administrative approval without returning to the Board of County Commissioners for another vote.
The submission does not mean construction has been approved. The project must still satisfy the county’s review requirements before it can move forward.
Zoning Decision Cleared Earlier Hurdle
The latest development follows an Aug. 27 decision by the El Paso County Board of County Commissioners, which voted 4-1 to determine that the proposed Buc-ee’s qualifies as an allowed use in the property’s C-1 commercial zoning district.
The decision resolved a dispute over how the proposed business should be classified under the county’s Land Development Code. Buc-ee’s had sought recognition as a convenience store, while county planning officials initially said they could not determine whether the large travel center fit that definition.
The commissioners’ decision addressed only the land-use classification. It did not approve the project’s site layout, traffic plans, utilities, drainage, signage or other development details.
Community Concerns Remain
The proposal has faced resistance from residents concerned about the potential effects of a large travel center on the surrounding area, including traffic and changes to the character of the Tri-Lakes community.
The project also previously faced opposition in Palmer Lake, where Buc-ee’s initially pursued annexation of the property. The company withdrew that request in February after community pushback.
Buc-ee’s has continued pursuing the El Paso County location despite those challenges. The proposed site is near the I-25 and County Line Road corridor, north of the Colorado Springs area.
With the site development plan now under review, the county’s next steps will focus on whether the proposal meets applicable technical standards. The outcome of that review will help determine whether the project can advance through the development process.